Large Manufacturing Facility
Challenge
The most significant projects have been a chiller plant and a large campus including offices, distribution, and a production facility. The campus building contains approximately 250,000 sq. ft. under roof.
Solution
The chiller plant includes:
- 5,000 tons of cooling
- Extensive BIM use allowing us to pre-fabricate the main piping systems
The campus building includes:
- 2,500 tons of cooling
- 6 boilers serving a hot water system
- 12 air handling units with the largest being over 60,000 cfm each
- An extensive snow melt system
- Humidification systems
- Associated ductwork and piping systems
A Closer Look
We also worked closely with the company to design and install the building automation system for the campus facility.